Project Update - April 20, 2018
Published on April 20, 2018

Trims
Differed:
- 312 oak trees to prevent oak wilt (21% of the project)
Completed:
- About 822 trims (56% of the project)
- Maintenance Districts: 0, 1, 2, 3, 5, 6, 17, 21, 22, 23, 25, 26, 27, 28, 30, 34, 35, 36, 37, 38, 39, 40
- Fairplains, Greenwood, and Oak Hill Cemeteries
- Aberdeen, Ah-Nab-Awen, and Briggs Parks
Working:
- Maintenance Districts: 4, 9, 11, 19, 20
- Riverside and Richmond Parks as weather allows
Removals
Completed:
- About 1083 removals (76% of the project)
- Maintenance Districts: 0, 1, 5, 6, 10, 11, 12, 13, 14, 15, 16, 19, 20, 21, 22, 23, 25, 24, 26, 27, 28, 30, 31, 32, 25, 36
- Parks: Ah-Nab-Awen, Aberdeen, Briggs, Canal, Cherry, Campau, McKay-Jaycee, MLK, Mulick, Midtown Green, Veterans, Plaster Creek Family, Garfield, Lincoln, Dickinson, Richmond, Tremont, and Clemente
- Oak Hill North, Oak Hill, Oak Grove, and Woodlawn East and West Cemeteries
Working:
- Maintenance Districts: 2, 3, 14, 17, 18, 25, 30, 32
- Fuller Park, Huff Park, Mary Waters Park, and Riverside Park
- Oakhill South and Fairplains Cemeteries
Stumps (from removals)
Completed:
- 555 stumps (39% of the project)
Other Stumps (backlogged)
Completed:
- 106 stumps (14% of awarded stumps)