Project Update - February 9, 2018
Published on February 09, 2018
Trims
Completed:
- About 578 trims (39% of the project)
- Maintenance Districts: 2, 5, 6, 17, 25, 26, 27, 28, 38, 39, 40
- Fairplains Cemetery
Working:
- Maintenance Districts: 1, 3, 34, 35, 37
- Riverside Park, Richmond Park, and Greenwood Cemetery as weather allows
Removals
Completed:
- About 616 removals (44% of the project)
- Maintenance Districts: 5, 6,10, 11
- Ah-Nab-Awen, Briggs, Plaster Creek Family, Garfield, Lincoln, Dickinson, and Clemente Parks
- Oak Hill Cemetery North and Woodlawn Cemetery East
Working:
- Maintenance Districts: 0, 1, 2, 3, 12, 14, 17, 18, 20, 35
- Riverside Park and Mary Waters Park
- Oak Grove Cemetery
Stumps (from removals)
Completed:
- 32 stumps (2% of the project)
- Dickinson, Ah-Nab-Awen, Briggs, Dickinson, and Plaster Creek Family Parks
Working (as weather allows):
- Maintenance Districts: 0, 5, 17
- Lincoln Park
Other Stumps
Contract awarded to three companies and includes street locations throughout Grand Rapids.