Project Update - March 9, 2018

Published on March 09, 2018

Priority I Forestry Initiative 

Trims

Completed: 

  • About 663 trims (45% of the project)
  • Maintenance Districts: 2, 3, 5, 6, 17, 25, 26, 27, 28, 34, 38, 39, 40
  • Fairplains Cemetery

Working:

  • Maintenance Districts: 1, 21, 22, 23, 35, 37
  • Riverside Park, Richmond Park, and Greenwood Cemetery as weather allows

Removals

Completed:

  • About 876 removals (62% of the project)
  • Maintenance Districts: 0, 1, 5, 6, 10, 11, 12, 13, 14, 20, 21, 22, 23, 26, 27, 28
  • Parks: Aberdeen, Ah-Nab-Awen, Briggs, Campau, Canal, Cherry, Clemente, Dickinson, Garfield, McKay-Jaycee, Lincoln, MLK, Mulick, Midtown Green, Veterans Memorial, Tremont, Richmond, and Plaster Creek Family
  • Oak Hill Cemetery North and Woodlawn Cemetery East

Working:

  • Maintenance Districts: 2, 3, 14, 16, 17, 18, 25, 30, 32, 35
  • Fuller Park, Mary Waters Park, and Riverside Park
  • Oak Grove Cemetery, Woodlawn Cemetery West, Oakhill South, and Fairplains Cemetery

Stumps (from removals)

Completed:

  • 320 stumps (23% of the project)

Other Stumps (backlogged)

Completed:

  • 42 stumps (18% of awarded stumps)